December 1: Groundbreaking
December 11: Foundation installed
February 13: Basement concrete slab poured
February 26: Backfilling complete
March 1: Framing began
March 24: Plywood sheathing installed to enclose
March 28: Exterior doors and windows installed
March 29: Shingled roof completed
April 10: Front porch footings complete
April 12: Garage floor poured
April 23 Front porch construction began
April 30: Garage doors installed
May 2: Siding installation begins
May 8: Attic insulation begins
May 15: Staircases installed
May 22: Front porch completed
May 23: Siding completed
June 11: Insulation completed
June 13: Drywall begins
Coming soon...gutters, flooring, and cabinetry. Stay tuned!